MainOne, one of the undersea cable companies affected by service disruptions due to multiple cable cuts, has said it might take between two and three weeks to fix the damaged portions of the cable.
In a note on Friday, the cable company said some form of seismic activity on the seabed resulted in a break to the cable.
It added that preliminary findings and further investigations revealed that the fault occurred due to an external incident that resulted in a cut on the submarine cable system, in the Atlantic Ocean offshore Cote DIvoire along the coast of West Africa.
We have a maintenance agreement with Atlantic Cable Maintenance and Repair Agreement (ACMA) to provide repair services for the submarine cable.
First identify and assign a vessel, the vessel has to retrieve the necessary spares required for repair, and then sail to the fault location to conduct the repair work.
Next, in order to complete the repair, the affected section of the submarine cable will have to be pulled from the seabed onto the ship where it will be spliced by skilled technicians.
Post-repair, joints will be inspected and tested for any defects and then the submarine cable is lowered back to the seabed and guided to a good position.
This process might take one to two weeks for repairs while about two to three weeks of transit time may be required for the vessel to pick up the spares and travel from Europe to West Africa once the vessel is mobilized, the company said.
On what could have specifically caused the outage, the company said most submarine cable faults occur as a result of human activities such as fishing and anchoring in shallow waters near shore, natural hazards such as earthquakes, landslides, and then equipment failure.
Given the distance from land, and the cable depth of about 3kms at the point of fault, any kind of human activity “ ship anchors, fishing, drilling etc has been immediately ruled out.
Our preliminary analysis would suggest some form of seismic activity on the seabed resulted in a break to the cable, but we will obtain more data when the cable is retrieved during the repair exercise, MainOne said.
On whether it was intentionally sabotaged, the company said it was most unlikely.
Not likely given the location and cable depth, and as indicated above, we have strong indications on probable cause, the company said.
On thespecific sea vessels are being allocated to repair the damage, the company said: We are working with Atlantic Cable Maintenance and Repair Agreement (ACMA) who will deploy the vessel and are unable to provide more information at this time.(Courtesy, excluding headline, The Nation)
NEWS EXPRESS is Nigeria’s leading online newspaper. Published by Africa’s international award-winning journalist, Mr. Isaac Umunna, NEWS EXPRESS is Nigeria’s first truly professional online daily newspaper. It is published from Lagos, Nigeria’s economic and media hub, and has a provision for occasional special print editions. Thanks to our vast network of sources and dedicated team of professional journalists and contributors spread across Nigeria and overseas, NEWS EXPRESS has become synonymous with newsbreaks and exclusive stories from around the world.