NEWS EXPRESS is Nigeria’s leading online newspaper. Published by Africa’s international award-winning journalist, Mr. Isaac Umunna, NEWS EXPRESS is Nigeria’s first truly professional online daily newspaper. It is published from Lagos, Nigeria’s economic and media hub, and has a provision for occasional special print editions. Thanks to our vast network of sources and dedicated team of professional journalists and contributors spread across Nigeria and overseas, NEWS EXPRESS has become synonymous with newsbreaks and exclusive stories from around the world.

























Loading banners
Loading banners...


railway line
The Federal Government has disclosed plans to conduct a three-month test run of the Kaduna-Kano railway corridor.
The Permanent Secretary of the Ministry of Transportation, Engr. Funso Adebiyi disclosed this during an inspection tour of the Kaduna-Kano railway corridor ahead of the commissioning in December.
Adebiyi said the test run is intended to assess the structural integrity of the railway infrastructure and ensure that the system can sustain regular operations before the commencement of commercial services.
He also said the government was considering running the service free of charge during the test period, subject to the approval of President Bola Tinubu.
Speaking on the pace of the project, Adebiyi said concerns raised during an earlier inspection had been addressed by the contractors, particularly those relating to passenger safety, lighting and maintenance.
He said all the toughened glass previously specified for areas occupied by passengers had been replaced with laminated glass to reduce the risk of injury in the event of breakage.
He said: “The change was necessary because toughened glass could shatter under certain conditions, including exposure to high temperatures or accidents, whereas laminated glass would minimise the danger to passengers”.
He added that the lighting system had also been upgraded to ensure that the bulbs installed had a minimum service life of three years, in line with the earlier directive.
Adebiyi also disclosed that arrangements were being made to strengthen maintenance capacity through the provision of man lifts and the training of Nigerian Railway Corporation (NRC) personnel.
He said the NRC had been asked to nominate trainable engineers who would undergo intensive training in railway station operations, adding that he would personally participate in the training and examination process.
He said only personnel who successfully pass the examinations would be retained for the operational responsibilities, after which the NRC would take over the management of the railway system.
On accessibility, the official confirmed that four lifts had been ordered to assist persons with disabilities in accessing different sections of the terminal.
Addressing concerns about the outstanding connection between Jaji and Kaduna, he explained that the project had encountered challenges associated with the security situation and land requirements, necessitating the construction of a bridge.
He however, said the bridge was being constructed on-site and had reached an advanced stage.
He added that It was the major outstanding component preventing the railway from extending fully into Kaduna town.
He expressed optimism that the remaining section would be completed within four to six months.
Comment on other corridors, Adebiyi disclosed plans by the federal government to flag off construction of the Ibadan-Osogbo-Ilorin-Minna corridor within the next two months.
On the Itakpe-Warri-Abuja corridor, he said the proposed Itakpe-Abuja extension was at an advanced stage and awaiting presidential approval for construction to commence.
The Director-General of the Debt Management Office (DMO), Patience Oniha, said the visit was part of the agency’s responsibility to assess capital projects financed through government funding.
Oniha said the improved transportation infrastructure would create economic opportunities beyond the movement of passengers and cargo.
According to her, businesses, traders and small-scale entrepreneurs along the railway corridor stand to benefit from increased economic activities generated by the transportation network.
On the need for additional funding, Oniha said proposed projects would be evaluated and subjected to the necessary appraisal and approval processes before funding could be provided.
A representative of CCECC, Mark Xu assured that the team would continue working towards delivering the project ahead of the planned December commissioning. (The Nation)