NEWS EXPRESS is Nigeria’s leading online newspaper. Published by Africa’s international award-winning journalist, Mr. Isaac Umunna, NEWS EXPRESS is Nigeria’s first truly professional online daily newspaper. It is published from Lagos, Nigeria’s economic and media hub, and has a provision for occasional special print editions. Thanks to our vast network of sources and dedicated team of professional journalists and contributors spread across Nigeria and overseas, NEWS EXPRESS has become synonymous with newsbreaks and exclusive stories from around the world.

Damaged Kugbo Bus Terminal, Abuja
The Kugbo Bus Terminal inaugurated by Nyesom Wike, Minister of Federal Capital Territory (FCT), in June, was damaged yesterday, Tuesday, April 7, 2026.
The News Agency of Nigeria (NAN) reports that the heavy rain began around 3:30 p.m.
The roof of the terminal, which has not been put in use, was pulled down by the wind.
The debris spread to the major road further compounding traffic chaos as workers were returning home.
The development caused heavy traffic on both sides of the dual carriageway, while scavengers were seen carting away valuable parts of the roof and other valuables deposited on the road.
Confirming the incident, Mr Lere Olayinka, Senior Special Assistant to the FCT Minister on Public Communications and Social Media, said that the rainstorm also caused minor damage to the Nyanya pedestrian bridge and some buildings in the area.
Olayinka said in a statement that preliminary reports showed no one was injured, and no vehicle was damaged.
He said that the FCT Minister, Nyesom Wike, had directed that security men be deployed to the scene, to prevent breakdown of law and order and to ensure free flow of traffic.
He assured that immediate action would be taken towards fixing the damages caused by the rainstorm.
NAN reports that the Kugbo bus/taxi terminal is one of the three newly built terminals inaugurated in June 2025.
Wike inaugurated the construction of bus and taxi terminals in Mabushi, Central Business District (CBD), and Kugbo in July 2024, to enhance commuter safety and convenience.
Mr Biodun Otunola, Managing Director and Chief Executive Officer of Planet Project Ltd., explained that the Kugbo and Mabushi terminals were designed to process more than 10,000 passengers each day.
Otunola, the contractor, added that the terminals were also designed to accommodate 120 buses and taxis each daily for both intercity and intra-city travel.
He, however, said that the terminal in the CBD was different, adding that it was essentially designed for intra-city operations.
The contractor said that each of the three terminals would employ at least 100 persons.
On the operations of the terminals, Wike, had on March 27 said that the completed terminals would begin operations soon following approval of the Federal Executive Council (FEC).
The Minister explained that President Bola Tinubu and FEC had approved the management of the bus terminals in Mabushi and Kugbo, based on a Public-Private Partnership arrangement.
He said that the bus terminals, though completed and inaugurated in 2025, could not begin operations because their management was above ministerial approval. (Pieced together from reports by Daily Trust and NAN)